Category: Event (Page 1 of 42)

Week of July 15th

This week had a lot of progress. Finished framing & sheathing the roof. The roofers started. The plumbers put the in-floor plumbing in the basement floor getting ready to pour the floors next week. Front and back walls were built getting ready for windows next week. Xcel Energy ran the conduit for power.

Next week will be busy. Hope to put the basement, garage and patio floors. The septic system will go in next week. In floor heat tubing will be laid down for the basement floor. Power should get hooked up. We may even get a driveway next week.

Drone Video
Timelapse Video

Views: 26

Timelapse: Roof Trusses

Timelapse for the week of July 8th. Crane on Monday to lift all of the main roof trusses. Framed a bunch of interior details that we cannot see on the timelapse. Framed up most of the overhangs and added roof sheathing.

I changed the time-lapse to take a picture ever 10 seconds. This extends the video to about 2-1/2 minutes per day. A little longer video, but the detail is much better and smoother.

Views: 44

July 4th Week: More Framing

This is a short 3-day week, but a lot of progress. Unfortunately, some of it is hard to see in the timelapse video. The interior walls were finished including the framing for the see through fireplace.

The electric meter socket was installed and is ready for Xcel Energy to bring in power next week or early the following week.

They guys put up some of the roof trusses showing the 12:12 roof line. Really looking great.

Next week, the crane will be onsite Monday to lift and install the remainder of the roof trusses.

Views: 31

Framing and Roof Truss Delivery

This week, the basement bearing walls were put up, the floor joists were set and the floor sheathing was laid. Most of the exterior walls were framed and some of the interior walls were framed.

The first video is a the timelapse for all 5 workdays. The new battery worked good for the camera. It lasted all week with lots of power to spare.

The second video shows the roof trusses being delivered. it was a bit exciting. The delivery truck / trailer could not get all the way to the top of the hill, and ended up getting stuck on the side hill. In the end, the guys did a great job and everything was delivered. Ready for more framing next week.

Timelapse: Framing the week of June 24th.

Views: 38

Timelapse: Backfilling

I wanted to see the progress better over time, so I purchased an ATLI 1080P Time Lapse Camera on Amazon. This little guy can shoot up to a week of video / photos. (if you take 1 photo every 30 minutes) on a single charge. I wanted more detail, so the first day, it took 1 image every minute, but that was too choppy. The second day, it took 1 image ever 30 seconds. I set it up on a schedule to only shoot from 7:30am to 6:00pm or 10-1/2 hours per day. The battery lasted just over 2 days.

I mounted it 25 feet up a tree to have a good view of the worksite and took 2 days of video.

Camera Setup with external battery.

With framing starting on Monday, I wanted to figure out a way to have it record for 5 days without having to touch it. I also wanted images every 15 seconds. So, I bought a big battery, some wire, a USB C converter and silicone rainproof putty and wired to camera directly to the new external battery. Testing looks good. If it all works to plan, I will post all the details next week.

Views: 94

« Older posts

© 2024

Theme by Anders NorenUp ↑