Week of July 15th

This week had a lot of progress. Finished framing & sheathing the roof. The roofers started. The plumbers put the in-floor plumbing in the basement floor getting ready to pour the floors next week. Front and back walls were built getting ready for windows next week. Xcel Energy ran the conduit for power.

Next week will be busy. Hope to put the basement, garage and patio floors. The septic system will go in next week. In floor heat tubing will be laid down for the basement floor. Power should get hooked up. We may even get a driveway next week.