Wow. Lots done this week. The roof was completed. The front porch is mostly done as well as the back deck. The basement floor was insulated with rigid foam and the in-floor heating coils and manifold were installed. The basement floor and Patio cement were poured.
Most of the windows were installed along with the fireplace.
The septic system was competed in 1/2 of a day on Tuesday. There is a timelapse video below short with my drone. There are also pictures here.
Views: 95
Very nice. When are you expected in?
Our deadline is October 16th.
If everything stays on track, we think we can get occupancy mid-September. Fingers Crossed!!
Great update!